Electrical team takes care of day to day maintenance of electrical systems and also undertake major/minor electrical works for the campus.
Name | Responsibilities |
---|
Emergency Mode (Time: 1 - 3 days): | The End user gets the approval directly from Director for executing the work on quotation or nomination basis by explaining the urgency of the work to Director. IWD will then get the necessary technical approval as well as the works within one to seven days |
Fast Mode: (Time: 3 - 15 days): |
Option 1: If the approved value of work is less than 25000, such works are executed by calling quotations from eligible parties and executed within three to fifteen days. Option 2: If the end-user provide all the necessary materials, IWD will then execute the work using our manpower |
Normal Tender Mode: (Time: 4 - 12 Months): | The following procedure has to be followed by IWD, It is a time taking process therefore the end-users are requested to plan well ahead and not in the neck of the moment. |